Who needs a Georgia utility contractor license, what the utility manager and foreman certificates require, the fees, and the clock that starts when the manager leaves.
Georgia licenses underground utility work separately from general contracting. A company that builds or repairs water, sewer, gas, power or communication lines five feet or more below ground needs a utility contractor license from the Division of Utility Contractors, and it cannot get one until a certified utility manager works for it full time. This guide covers the three utility credentials, the company rules rewritten by Senate Bill 553 on July 1, 2026, the fees, and what happens when the manager leaves.
The utility license sits beside the general contractor licenses covered on our Georgia contractor license page. If your company also builds structures, you may need both.
At a glance
- Who issues it: the Division of Utility Contractors of the State Construction Industry Licensing Board, under O.C.G.A. 43-14-10 as reenacted July 1, 2026.
- What triggers it: utility systems at least five feet underground installed by trenching or open cut, plus treatment plants, reservoirs and pump stations that serve paying customers (SB 553).
- Three credentials: a company license (no exam), a utility manager certificate (exam), and a utility foreman certificate.
- The company rule: a full time utility manager at each permanent office, and a certified manager or foreman on every job site.
- Company application: $50 plus a $10 processing fee, filed online through GOALS (Georgia Secretary of State).
What Counts as Utility Contracting in Georgia
The definition decides whether you need this license at all. Under O.C.G.A. 43-14-2(33), a utility system is either of two things.
| Part | What it covers | Depth rule |
|---|---|---|
| Buried systems | Gas, electrical distribution, communication, water supply, sanitary sewer and drainage lines installed or reached by trenching, open cut, cut and cover or similar methods | At least five feet underground |
| Treatment and pumping | Reservoirs, filtration plants, water and wastewater treatment plants, landfill leachate systems and pump stations | No depth rule, but only where the system delivers or collects a product or service someone pays for |
The five foot line matters. A Georgia appeals court held in Brantley Land and Timber v. W and D Investments (2012) that trenching and installation shallower than five feet was not utility contracting. Shallow service work may still need an electrical, plumbing or low voltage license, so check the trade rule before you bid.
Utility contracting means undertaking to build, erect, alter or repair a utility system, or having someone else do it for you. A company that bids or offers that work is a utility contractor even before it signs a contract.
The Three Utility Credentials
Georgia splits utility licensing between the company and two individual certificates. The company license is the one owners search for, but it is only as good as the manager standing behind it.
| Credential | Who holds it | Exam | Main requirement |
|---|---|---|---|
| Utility contractor | The business | None | A full time utility manager and a written safety policy |
| Utility manager certificate | An individual employee | Yes, minimum score 70 | Three years of full time field experience and 12 hours of safety training |
| Utility foreman certificate | An individual employee | See note below | One year of full time experience under a utility manager and 12 hours of safety training |
A note on the foreman exam. The reenacted statute, O.C.G.A. 43-14-12(e), lists passing an examination with a minimum score of 70 among the foreman requirements. The board's own how to guide still describes initial foreman licensing without an exam. Until the division updates its guide, ask it which rule applies to your file before you schedule anything.
Utility Manager Certificate Requirements
The manager is the person who qualifies the company. Under O.C.G.A. 43-14-11(e), an applicant must meet all of these.
- Pass the utility manager examination with a minimum score of 70.
- Complete 12 hours of board approved safety training.
- Document at least three years of full time field experience building, altering or repairing utility systems: at least one year under a certified utility manager, then at least two more years while holding a utility foreman certificate.
- Provide employer affidavits verifying the experience.
- Provide identity and lawful presence documents and consent to a criminal background check with fingerprints.
Full time has a number now. O.C.G.A. 43-14-2(13) defines full time experience as at least 2,000 documented hours in a calendar year, and each 2,000 hours counts as one year. The board's older rule, 121-2-.08, also asks for three references and notarized letters from each employer listed on the application.
The manager exam
PSI administers the Utility Manager Examination after the board approves the application and issues an exam approval letter, which is good for one year. The PSI candidate handbook (November 2024) sets out the format below.
| Item | Utility manager exam |
|---|---|
| Scored questions | 80, plus 15 unscored pretest questions |
| Time | Four hours |
| Passing score | Scaled score of 70 |
| Reference books | Only titles on the board's current reference list |
PSI sets the exam fee and lists it when you register. Fees are set by the board or testing vendor and can change. Verify the current amount with the provider before you pay.
Utility Foreman Certificate Requirements
The foreman certificate is the first rung, and it is also the credential that lets a field supervisor run a crew. Under O.C.G.A. 43-14-12(e), an applicant needs one year of full time experience under a licensed utility manager, 12 hours of safety training, an employer affidavit, and the examination the statute lists. Board Rule 121-2-.10 says the safety course must run at least 12 hours of actual instruction and include competent person training in trenching and excavation and confined space entry.
The board's how to guide adds a law enforcement background check and letters from current and former employers. Foreman and manager certificates both require the safety training again at renewal.
The Company License and the Full Time Manager Rule
A utility contractor license goes to a sole proprietorship, partnership, LLC or corporation, not to a person. Under O.C.G.A. 43-14-10(f), the business must have a utility manager certificate holder who works for it full time and oversees the utility work of all its employees.
- One office, one manager at minimum. Each permanent office must be registered with the division, with a certificate holder stationed there full time.
- One company per manager. The division's application tells applicants that a utility manager may be associated with only one utility contractor and must be a regular, full time employee of that business.
- A safety policy on file. The company submits a written safety policy committing to state and federal safety rules, a safety program and regularly scheduled safety meetings for field crews.
- Background checks. Each owner, partner and officer signs the application's criminal history release, and filing the application is consent to a background check under 43-14-10(h).
A certified person on every job. No utility system may be built, altered or repaired unless a certified utility manager or utility foreman with a current certificate is physically at the job site, under 43-14-11(c) and 43-14-12(d). That applies to the whole job, not just the deep trench.
How to apply, step by step
- Hire or promote a utility manager certificate holder as a full time W-2 employee. The division's form says plainly not to apply for the company license before you have one.
- Register the business entity with the Georgia Secretary of State.
- Write and sign the company safety policy; each owner, partner and officer signs the certification.
- File the utility contractor application in GOALS with the Employment of Utility Manager form for each listed manager. The division no longer accepts paper applications.
- Answer any deficiency notice within 60 days, or the board may withdraw the application.
- Keep a certified manager or foreman on every job once the license issues.
Fees and Renewal
The board's published fee schedule lists these amounts. Fees are set by the board or testing vendor and can change. Verify the current amount with the provider before you pay.
| Item | Utility contractor | Utility manager | Utility foreman |
|---|---|---|---|
| Initial application | $50 plus $10 processing | $30 plus $10 processing | $30 plus $10 processing |
| Renewal | $75 | $75 | $35 |
| Late renewal | $100 | $100 | $45 |
| Lapsed under three years | $150 | $150 | $70 |
Utility licenses and certificates expire April 30 of odd numbered years, with a late renewal window in May. A utility contractor cannot renew until its utility manager has renewed, so the manager's renewal is the first item on the company's calendar every other spring. A manager whose certificate lapses three years or more must pass the exam again.
When the Utility Manager Leaves
This is where Georgia utility contractors lose licenses. The company and the manager both have a duty to notify the division when the connection ends, under O.C.G.A. 43-14-10(j).
| Step | Deadline | Source |
|---|---|---|
| Notify the division the manager has left | Within seven days of the last day of employment under the 2026 statute; the board's rule and FAQ still say five days | 43-14-10(k); Rule 121-6-.05 |
| First grace period to hire a new manager | 90 days | 43-14-10(k) |
| Request a second grace period for good cause | At least 15 days before the first period ends | Rule 121-6-.05 |
| Report the new hire | Within five days of hiring | Rule 121-6-.05 |
| Total grace allowed | No more than 180 days in any two year period | 43-14-10(k) |
File within five days. The statute and the board's rule disagree on the notice window, and five days satisfies both. Miss the notice, or run out the grace period without a hire, and the company loses the right to do utility contracting and faces suspension or revocation after a hearing.
Good cause for the second 90 days means things like a medical or natural emergency or a manager candidate whose certificate application is pending. The request has to describe the company's hiring efforts and its plan to hire within the next 90 days.
Penalties for Unlicensed Utility Work
Georgia gave the utility division real money penalties in the 2026 rewrite. A person who violates a cease and desist order for utility contracting faces a fine of up to $5,000 for each violation, and each day of unlicensed practice counts as a separate violation, under O.C.G.A. 43-14-17(e). The chapter also lists license denial, suspension, revocation, administrative fines and injunctions as available discipline.
The rewrite also made it express grounds for discipline to let an unlicensed person or entity use a license, which is why the manager has to be a real employee doing real oversight. Our guide to the 2026 Georgia law changes covers that provision across all five specialty divisions.
Where a Qualifying Agent Fits
The utility manager is Georgia's qualifier for this license, and the statute is built around a W-2 relationship: full time, overseeing every employee's utility work, stationed at the office. A company that grows past its founder's experience, opens a second office, or loses its manager needs a certified person on payroll fast, and the 90 day clock does not wait.
That is the gap The Licensing Company fills. Our founders, Marshall Schofield and Jeremiah Jaskulski, place experienced qualifiers as full time W-2 employees who supervise the work the license covers. If your utility manager is leaving or you are entering the Georgia market, start with hiring a qualifying agent, and see our Georgia qualifying agent guide for how the general contractor side works.
Frequently Asked Questions
Do I need a utility contractor license for work shallower than five feet? Not for buried line work under the utility definition, which starts at five feet. Treatment plants, reservoirs and pump stations serving paying customers are covered at any depth, and shallow work may still need an electrical or plumbing license.
Can the owner be the utility manager? Yes, if the owner holds the certificate and works in the business full time overseeing all utility work. The rule is about the certificate and the full time role, not about ownership.
Can one utility manager qualify two companies? No. The division's application says a manager may be associated with only one utility contractor and must disassociate from the current company before qualifying another.
How much does it cost to get a Georgia utility contractor license? Board fees are modest; the table above lists them. The real cost drivers are the manager's salary and benefits, safety training, insurance your customers and project owners require, and the time lost if you start without a manager. For help planning around those, talk with us through hiring a qualifying agent.
How long does it take? The company license is reviewed administratively once a manager is in place, but a manager candidate needs three years of documented field experience and a passed exam first. If you do not already have one on staff, finding a certified manager is the long pole.
Sources
All retrieved 2026-11-16.
- Georgia SB 553 (2026), reenacting O.C.G.A. Title 43, Chapter 14 (Office of the Governor, signed legislation)
- Utility Contractors FAQ (Georgia Secretary of State)
- How To Guide: Utility Contractors (Georgia Secretary of State)
- Georgia State Board of Utility Contractors
- Board Rules Chapter 121-2, Qualifications for Licensure
- Ga. Comp. R. and Regs. R. 121-6-.05, grace period for utility contractors (Justia Regulations)
- Utility Manager Examination Candidate Information Handbook, November 2024 (PSI)
- Specialty contractor fee schedule (Georgia Secretary of State)
- Nelson Mullins, 2026 Georgia Construction Legislation
Disclaimer: This article is provided for educational and informational purposes only. It does not constitute legal advice, licensing guidance, or an offer of services. Licensing requirements vary by jurisdiction. For specific compliance questions, contact The Licensing Company for a confidential consultation.
Tell us the state and the trade. A member of the team calls you back.
We confirm what your board requires for your situation, then match a licensed qualifier who joins your company as a full time W-2 employee. Rather talk now? Call 615-219-2110.
Tell us your state and trade